Bruce to Milton Power Line
2012 Rank: 45
2011 Rank: 38
Sector: Transmission
Location: Kincardine to Milton, Ontario
Owner: Hydro One Networks
Key Players:
Contractor: Valard Construction (power line construction)
Other: Dillon (prime consultant)
Funding: Public
Status: Construction has begun on lands where Hydro One has acquired property rights and the necessary approvals, with expected completion in 2012.
Description:
A 180 km, double-circuit, 500 kV transmission line is being built on a widened existing corridor between the Bruce Power Facility in Kincardine and Hydro One’s switching station in Milton. This project represents the largest expansion to Ontario’s transmission system since the late 1970s. In July of 2011 construction reached the halfway point. The project will allow an additional 3,000 MW of power to flow onto the Ontario power grid. This project represents the first time that Hydro One has used a third-party contractor, Valard, to complete a transmission project.