Georgetown South Track Layout and Grading Design Assignment
$1.5 billion
2012 Rank: 20
2011 Rank: 27
Sector: Rail
Location: Toronto, Ontario
Owner: Metrolinx/GO Transit
Key Players:
Project/Construction Manager: Hatch Mott MacDonald (construction management on five out of nine segments)
Engineer: AECOM (engineering services for contract administration and construction management); Delcan (prime consultant—Weston Tunnel); Hatch Mott MacDonald (engineering assignment for layout and grading design);
DBF Team: A joint venture between Aecon Group Inc. and Dufferin Construction Company, a division of Holcim;
Other: Morrison Hershfield (contract administration and site supervision); Golder Associates (EA)
Funding: Public
P3 (DBF) Air Rail Link
Federal Canadian Strategic Infrastructure Fund and Investment Strategy Fund
Provincial Capital allotment to Metrolinx/GO Transit
Description:
This expansion will address both the forecasted increase in GO Transit ridership along the corridor as well as the Union-Pearson Air Rail Link. Because of the size and complexity of the program, Metrolinx divided work on the corridor into nine individual segments, five of which have been awarded to Hatch Mott MacDonald. The contract is for detailed design and construction management of 14.8 km of corridor, which includes 30 km of new track, numerous retaining walls, sound walls, utility relocations and, site grading and drainage. Metrolinx and Infrastructure Ontario awarded the design-build-finance (DBF) contract for the Air Rail Link in late October 2011, financial close is expected in 2012 with construction following shortly afterward.