Labrador-Island Transmission Link

Back to 2013 Project List


Ranking for 2013: 17

Industry Sector: Energy

Specific Sector: Transmission

Range: $1 billion - $5 billion

Project Value: $2,100,000,000

Government Funds Involved:

Funding Source: Private

Location: Muskrat Falls, Labrador to Soldiers Pond, Newfoundland and Labrador

Estimated End Date of Substantial Completion: 2016

LEED:


This 900 MW, 1,135 km transmission line across the Strait of Belle Isle will connect the Muskrat Falls Hydroelectric Project with Soldiers Pond on the island of Newfoundland. It will facilitate the transmission of electricity to Nova Scotia and on to export markets in the United States.

According to Nalcor, the in-service date for this project is 2016. However, Hydro Quebec filed a motion with Quebec Superior Court on July 22, 2013, claiming it has exclusive rights to purchase the power and energy produced by Churchill Falls Generating Station until 2041 and that Hydro Quebec has the right to control the output of Churchill Falls to optimize its own needs.

In November 2013, after an environmental assessment, the federal government said the project can continue with the regulatory approval process.