Upper Lillooet Hydro Project

Back to 2017 Project List


Image Credit: Innergex

Ranking for 2017: 86

Industry Sector: Energy

Specific Sector: Hydroelectric

Range: 0 - $500,000,000

Project Value: $491,600,000

Government Funds Involved:

Funding Source: Private

Location: Boulder Creek, Upper Lillooet River, British Columbia

Estimated End Date of Substantial Completion: 2016

LEED: N/A


This hydro project includes two run-of-river generation facilities: the 81.4-MW Upper Lillooet River Hydroelectric Facility and the 25.3-MW Boulder (Pebble) Creek Hydroelectric Facility. Each facility will divert partial flows from the river through an intake structure directly to the turbines and generating equipment located in each powerhouse. The water will then be returned to each respective river and creek. A single, 230-kV transmission line will be constructed to connect the electricity generated to the BC Hydro grid. The project will deliver electricity on the basis of a 40-year electricity purchase agreement.

Site preparation has been completed at the two powerhouses, and access roads have been built. Both the downstream tunnel portal at Boulder Creek and the diversion channel at the Upper Lillooet intake structure are underway. Downstream tunnel drilling and blasting has started, and drilling and blasting continues at the Boulder Creek facility. Approximately half of the transmission line has been completed so that temporary back-fed power can be used to support construction activities and the temporary camp facility for project workers. The construction has been scheduled from October 2013 to the end of 2017, when commercial operation is expected to commence.