Sunrise Natural Gas Processing Plant

Back to 2016 Project List


Ranking for 2016: 54

Industry Sector: Energy

Specific Sector: Natural Gas

Range: $500,000,000 - $1 billion

Project Value: $860,000,000

Government Funds Involved:

Funding Source: Private

Location: Montney Region, British Columbia

Estimated End Date of Substantial Completion: 2017

LEED: Certification


This new plant is one of three gas plants that Veresen plans on building in the Dawson Creek region. The Sunrise plant is expected to process 400 million cubic feet of gas per day, while Tower, with approval expected in late 2015, would be 200 million cubic feet a day. The existing Saturn plant would be expanded to allow for an additional 400 million cubic feet of gas per day.

Construction of the Sunrise gas plant has commenced, with the facility expected to be in service in late 2017.


Project Manager

Contractor

Engineer

© 2017 Top100 Projects. All rights reserved. Site Admin · Entries RSS · Comments RSS
Powered by WordPress · Designed by Theme Junkie