Capital Regional District Sewage Treatment Plant Program
$782 million 2012 Rank: 37 2011 Rank: 32 Sector: Water/Wastewater Location: Southern Vancouver Island, British Columbia Owner: Capital Region District Key Players: Engineer: C N Ryzuk & Associates (geotechnical consultant; Westland Resource Group, Associated Engineering, Kerr Wood Leidal Associates (consultants) Other: CH2M HILL (preliminary planning/study); Ernst & Young (business case); Stantec (business case and technical [...]
Union Station Train Shed Revitalization Project
$228 million 2010 Ranking: NEW Sector: Rail Location: Toronto, Ontario Owner: Metrolinx/GO Transit Key Players: Aecon (refurbishment of tracks and platforms, installation of new steel roof and glass atrium ); Halcrow Yolles, part of Halcrow Group (design consultant); Zeidler Partnership Architects (architectural sub-consultant); Read Jones Christoffersen (contract administration); Parks Canada (heritage preservation); Morrison Hershfield (construction [...]
The Waneta Expansion
$900 million 2012 Rank: 34 2011 Rank: 31 Sector: Hydroelectric Location: At the confluence of the Pend d’Oreille and Columbia Rivers, south of Trail, British Columbia Owner: Fortis, Columbia Power Corporation and Columbia Basin Trust Key Players: Project/Construction Manager: SNC-Lavalin (project manager) Engineer: Golder Associates (environmental consulting engineers), Hatfield Consultants Contractor: Aecon (civil design, construction); [...]
Port Mann Main Water Supply Tunnel—Fraser River Crossing
$240 million 2010 Ranking: NEW Sector: Water/Wastewater Location: Vancouver, British Columbia Owner: Metro Vancouver Key Players: Hatch Mott MacDonald (project manager); Ausenco Sandwell with Jacobs Associates (engineer); Golder Associates (geotechnical investigation and design services as a subconsultant to Ausenco, EA and permitting) Funding: Public Status: Design has been completed; a contractor is being selected in [...]
RCMP E division Headquarter Relocation Project
$966 million 2012 Rank: 32 2011 Rank: 29 Sector: Justice Location: Surrey, British Columbia Owner: Government of Canada Key Players: Engineer: Morrison Hershfield (building envelope) Architect: Kasian Architecture, AECOM (architecture services to Kasian) Contractor: Bird Construction, Bouygues Building Canada DBFM Team: Green Timbers Accommodation Partners—Bird Construction, Bouygues Building Canada, HSBC Infrastructure, ETDE Facility Management Canada [...]
Sainte-Justine University Hospital Centre Modernization
$995 million 2012 Rank: 31 2011 Rank: 28 Location: Montreal, Quebec Sector: Health Care Owner: Sainte-Justine University Hospital Centre Key Players: Project/Construction Manager: TDC Consortium—Tecsult (AECOM), DECASULT, and CIMA+ (project manager) Engineer: Pellemon/Bouthillette; Parizeau et associés (electrical, mechanical); SKD/NCK Consortium— Saïa, Deslauriers, Kadanoff, Leconte, Brisebois, and Blais/Nicolet Chartrand Knoll (civil, structural); Architect: Brière ; Demontigny ; Gilbert [...]
CentrePort Canada Highways
$262.5 million 2012 Rank: 96 2011 Rank: 91 Sector: Highway Location: Winnipeg, Manitoba Owner: Province of Manitoba Key Players: Engineer: Delcan (independent design review services for bridges); TBT Engineering (consulting engineer) Contractor: SNC-Lavalin (design-build) Other: MMM Group (Phase 1: functional planning study, procurement of a design-build contractor, construction oversight—grade separation for Canada Way) Funding: Public [...]
Georgetown South Track Layout and Grading Design Assignment
$1.5 billion 2012 Rank: 20 2011 Rank: 27 Sector: Rail Location: Toronto, Ontario Owner: Metrolinx/GO Transit Key Players: Project/Construction Manager: Hatch Mott MacDonald (construction management on five out of nine segments) Engineer: AECOM (engineering services for contract administration and construction management); Delcan (prime consultant—Weston Tunnel); Hatch Mott MacDonald (engineering assignment for layout and grading design); [...]
Riel Converter Station
$267 million 2012 Rank: 94 2011 Rank: 90 Sector: Transmission Location: Rosser, Manitoba Owner: Manitoba Hydro Key Players: Contractor: PCL (general contractor) Funding: Public Manitoba Hydro: $267 million Status: Under construction, with expected completion in 2014. Description: The station will serve as a backup for the Dorsey Converter Station, located west of the city near [...]
Autoroute 185
$1 billion 2012 Rank: 28 2011 Rank: 26 Sector: Highway Location: Rivière-du-Loup to the New Brunswick border, Quebec Owner: Ministry of Transportation of Québec Key Players: Engineer: AECOM (preliminary and final designs, work supervision); Other: AECOM (environmental impact study, hydraulic and hydrologic studies) Funding: Public Federal $222.5 million (Provincial/Territorial Base Funding) Provincial $1.08 billion Status: [...]