New Hospital for Sick Children

Rank 2024

34

Image Credit: Stantec-KPMB Architects

Industry Sector: Buildings

Project Type: Health Care

Project Value: $2.4 billion

Funding Source: Public

Provincial Funding: $2.4 billion

Province: Ontario

City / Region: Toronto

Estimated End Date of Substantial Completion: 2035

Dubbed ‘Project Horizon’ by SickKids, the three-phase project to rebuild and rehabilitate The Hospital for Sick Children in Toronto is well underway. There are three phases to the project, which are expected to take a total of 15 years to complete: A new 22-storey Patient Support Centre; The Peter Gilgan Family Patient Care Tower; and Renovations to the existing campus.

The new Patient Support Centre, was officially opened in September, 2023.The Patient Care Tower is scheduled for completion in 2029, followed by the completion of the Peter Gilgan Family Patient Care Tower in 2035. 

Project Owner: Hospital for Sick Children

Engineer: WSP (stage 1&2 master planning)

Project/Construction Manager: Infrastructure Ontario

P3 Team Members/Project Team: Patient Support Care Project Team - Construction Manager: PCL Constructors Canada Inc.; Structural Consultant: Entuitive; Electrical Consultant: Mulvey & Banani; Mechanical Consultant: The Mitchell Partnership; Demolition: Priestly Demolition, Peter Gilgan Family Patient Care Tower-Stage 2 Functional Programmer: RPG; Engineer: WSP (stage 1&2 master planning)

Other Key Players: Hanscomb (cost consultant); EY, HKA (management consultant)

Architect Names: B+H Architects (design architect)

Supplier Other: Stantec

Legal: Borden Ladner Gervais, McMillan LLP (for the owner)