Sunrise Natural Gas Processing Plant

Rank 2024

NR

Image Credit: Pipeline News North

Industry Sector: Energy

Project Type: Natural Gas

Project Value: $860 million

Funding Source: Private

Private Funding: $860 million

Province: British Columbia

City / Region: Montney Region

Estimated End Date of Substantial Completion: 2017

This new plant is one of three gas plants that Veresen plans on building in the Dawson Creek region. The Sunrise plant is expected to process 400 million cubic feet of gas per day, while Tower, would be 200 million cubic feet per day. The existing Saturn plant would be expanded to allow for an additional 400 million cubic feet of gas per day.

Construction of the Sunrise gas plant has commenced, with the facility expected to be service in late 2017.

Project Owner: Veresen Midstream Limited Partnership—Veresen (50%) and affiliates of Kohlberg Kravis Roberts & Co. LLP (50%)

Engineer: Fluor

Contractor: Ledcor

Project/Construction Manager: Encana

2017 Rank: 54

2016 Rank: 54