Quebec City University Hospital Center – Laval University

Rank 2021

34

Industry Sector: Health Care

Project Type: Health Care

Project Value: $1.97 billion

Funding Source: Public/Private

Provincial Funding: $1.78 billion

Municipal Funding: Foundation of the CHU of Quebec: $78 million; Parking: $109 million

Private Funding: $187 million

Province: Quebec

City / Region: Quebec City

Estimated End Date of Substantial Completion: 2025

In April of 2017, the Government of Québec formally announced plans to move forward with the replacement of the Hôpital Enfant-Jésus de Québec (Hospital of the Child Jesus) in Québec City. The project will consolidate the research and clinical activities of L’Hôtel-Dieu de Québec on the site of the new hospital. The first phase of the multi-phase project includes the construction of the Integrated Cancer Centre, along with a new generator building, power plant, and parking. 

In March 2020, construction was forced to shut down for a period of seven weeks due to the pandemic. It has not been confirmed whether this will impact the date of substantial completion for the project.

Project Owner: CHU de Québec-Université Laval

Engineer: SNC-Lavalin; CIMA+; Stantec

Other Key Players: Englobe (geotechnical/environmental investigation, quality control); GHD (vibration monitoring); Golder; Deloitte

2020 Rank: 31

2019 Rank: 28

2018 Rank: 23

KEY PLAYERS

Platinum Elite (20+ Projects)
Platinum (10-19 Projects)
Gold (6-9 Projects)
Silver (3-5 Projects)
Bronze (1-2 Projects)