Site C Clean Energy Project

Rank 2024

1

Image Credit: BC Hydro

Industry Sector: Energy

Project Type: Hydroelectric

Project Value: $16 billion

Funding Source: Public

Provincial Funding: BC Hydro: $16 billion

Province: British Columbia

City / Region: Near Fort St. John

Estimated End Date of Substantial Completion: 2025

The Peace River already has two large hydroelectric facilities (W.A.C. Bennett Dam and Peace Canyon Dam) that rely primarily on the Williston Reservoir for water storage. As the third project on the Peace River, Site C will rely on water already stored in the Williston Reservoir. This means that Site C will generate about 35 per cent of the energy produced at W.A.C. Bennett Dam, with only five per cent of the reservoir area. Construction on Site C began in July 2015. The project is more than 80 per cent complete and remains on-track to have all six generating units in-service by 2025. In July 2023, BC Hydro announced the completion of the earth fill dam. The earthfill dam stands about 60 metres tall (the height of a 20-storey building), stretches more than one kilometre across the Peace River and is about 500 metres wide at its base. The completion of the earthfill dam was one of the essential milestones required before we can begin filling the Site C reservoir. Filling the reservoir is one of the last steps in building Site C as it allows us to put the generating station, spillways, turbines and generators into operation. The reservoir will be more than 80 kilometres long and cover 5,550 hectares of land, with a total surface area of 9,330 hectares. It will take two to four months to fill the reservoir. 

Project Owner: BC Hydro

Engineer: Klohn Crippen Berger and AtkinsRéalis (engineering and design - dam and reservoir); Tetra Tech; BGC Engineering; WSP; R.F. Binnie & Associates; Lasalle | NHC (engineering and design - other); Associated Engineering (owner’s team - design); Wood E&I (WSP) (environmental/materials tester)

P3 Team Members/Project Team: DB(F)OM Team (Site C accommodation lodge): ATCO Two Rivers Lodging Group—ATCO Structures & Logistics Ltd. and Bird Design Build Construction Inc. Contractor: Peace River Hydro Partners—ACCIONA Infrastructure Canada, and Samsung C&T Canada (main civil works construction) AFDE Partnership—Aecon, Dragados, Flatiron, EBC (spillways civil works) Allteck Line Contractors Inc. (transmission line, Site C to Peace Canyon generating station) F&M Installations Ltd. (substation construction, balance of plant – electrical) Mitchell Installations Ltd. (balance of plant – mechanical)

Environmental Services: Golder-a WSP company (EA and permitting, archaeology, agriculture, fisheries and aquatics, socio economics); Pathfinder Endeavours Ltd.; Keystone Wildlife Research Ltd.; McMillen; RWDI Air Inc.; Knight Piésold; Industrial Forestry Service Ltd. (environmental and regulatory work); Morrison Hershfield (project review for EA authority); Hemmera

Other Key Players: AL Sims and Sons (road improvements); Aon (risk advisor); BTY Group (cost consultant); Hatch (environmental permitting); KPMG (lead commercial advisor); McElhanney (engineer, materials testing, environment, and survey); McMillen Jacobs Associates (dam/tunnel analyses: design of tunnel support); Morgan Construction and Environmental (north bank); Paul Paquette & Son’s Contracting (south bank); Kasian Architecture Interior Design and Planning Ltd.; WSP; ATCO Two Rivers Lodging Group (worker accommodation lodge); Paul Paquette and Son’s Contracting Ltd. (south bank clearing); Morgan Construction and Environmental Ltd. (north bank site preparation); Englobe (quality assurance services); Colliers Project Leaders; AGAT Labs; Hanscomb (cost consultant); Deloitte (risk advisor); HKA; EY (management consultant)

Supplier Other: Voith Hydro (turbine and generator); ATB Riva Calzoni Hydro Canada Inc. (hydromechanical equipment); Advanced Precast

Legal: Dentons Canada (owner’s counsel); Borden Ladner Gervais (legal advisor); Bennett Jones (acted for successful proponent); Singleton Urquhart Reynolds Vogel

Transmission Line Length (km): 154

MW Generation Power: 1100

2023 Rank: 1

2022 Rank: 1

2021 Rank: 7

2020 Rank: 6

2019 Rank: 4

2018 Rank: 4

2017 Rank: 5

2016 Rank: 2

2015 Rank: 1

2014 Rank: 1