Site C Clean Energy Project

Rank 2022

1

Image Credit: BC Hydro

Industry Sector: Energy

Project Type: Hydroelectric

Project Value: $16 billion

Funding Source: Public

Provincial Funding: BC Hydro: $16 billion

Province: British Columbia

City / Region: Near Fort St. John

Estimated End Date of Substantial Completion: 2025

This hydroelectric earthfill dam on the Peace River includes several components: an earthfill dam 1,050 metres long and 60 metres high, a 1,100-MW generating station and associated structures, an 83-kilometre-long reservoir, realignment of six sections of Highway 29, and two 77-kilometre transmission lines along an existing transmission line right-of-way, connecting Site C to the existing provincial power grid.

On February 26, 2021, the B.C. government announced a revised cost estimate of $16 billion and an expected one-year delay in the project’s in-service date (now 2025). The updated budget was approved by the provincial Treasury Board in June. Because of delays and impacts related to the pandemic, COVID-19 is the single largest contributor to the cost increase.

Despite the challenge of the COVID-19 pandemic, the project continued to advance in 2021. In the generating station and spillways civil works area, construction progressed with the ongoing placement of concrete in the powerhouse, intakes and spillways; installation of the penstock segments; and construction of the steel super-structure for the powerhouse. In the main civil works area, river diversion was successfully achieved in October 2020, and the upstream and downstream cofferdams were completed to their final elevations in spring 2021. Roller-compacted concrete (RCC) placements resumed at the dam and core buttress on the right bank; the entire RCC program is on track to be completed in fall 2021. Placements of dam core and fill material began on the left, centre section and right banks of the earthfill dam. Excavations in the approach channel also continued.

Project Owner: BC Hydro

Engineer: Klohn Crippen Berger and SNC-Lavalin (engineering and design - dam and reservoir); Tetra Tech; BGC Engineering; WSP; R.F. Binnie & Associates; Lasalle | NHC (engineering and design - other); Associated Engineering (owner’s team - design); Wood (consulting)

Contractor: Peace River Hydro Partners— ACCIONA Infrastructure Canada, Petrowest Corp., and Samsung C&T Canada (main civil works construction) AFDE Partnership—Aecon, Dragados, Flatiron, EBC (spillways civil works) Allteck Line Contractors Inc. (transmission line, Site C to Peace Canyon generating station) F&M Installations Ltd. (substation construction, balance of plant – electrical) Mitchell Installations Ltd. (balance of plant – mechanical)

P3 Team Members/Project Team: DB(F)OM Team (Site C accommodation lodge): ATCO Two Rivers Lodging Group—ATCO Structures & Logistics Ltd. and 
Bird Design Build Construction Inc.

Environmental Services: Golder-a member of WSP (EA and permitting, archaeology, agriculture, fisheries and aquatics, socio economics); Pathfinder Endeavours Ltd.; Keystone Wildlife Research Ltd.; McMillen; RWDI Air Inc.; Knight Piésold; Industrial Forestry Service Ltd. (environmental and regulatory work); Morrison Hershfield (project review for EA authority); Hemmera

Other Key Players: AL Sims and Sons (road improvements); Aon (risk advisor); BTY Group (cost consultant); Hatch (environmental permitting); KPMG (lead commercial advisor); EY (independent oversight advisor to the authority); McElhanney (engineer, materials testing, environment, and survey); McMillen Jacobs Associates (dam/tunnel analyses: design of tunnel support); Morgan Construction and Environmental (north bank); Paul Paquette & Son’s Contracting (south bank); Kasian Architecture Interior Design and Planning Ltd.; WSP; ATCO Two Rivers Lodging Group (worker accommodation lodge); Paul Paquette and Son’s Contracting Ltd. (south bank clearing); Morgan Construction and Environmental Ltd. (north bank site preparation); Englobe (quality assurance services); Colliers Project Leaders; AGAT Labs; Hanscomb (cost consultant); Deloitte (risk advisor); HKA

Supplier Other: Voith Hydro (turbine and generator); ATB Riva Calzoni Hydro Canada Inc. (hydromechanical equipment); Advanced Precast

Legal: Borden Ladner Gervais (owner's counsel); Bennett Jones (acted for successful proponent)

Transmission Line Length (km): 154

MW Generation Power: 1100

2022 Rank: 1

2021 Rank: 7

2020 Rank: 6

2019 Rank: 4

2018 Rank: 4

2017 Rank: 5

2016 Rank: 2

2015 Rank: 1

2014 Rank: 1

KEY PLAYERS

Platinum Elite (20+ Projects)
Platinum (10-19 Projects)
Gold (6-9 Projects)
Silver (3-5 Projects)
Bronze (1-2 Projects)