The West Park Healthcare Centre is a new 730,000-sq.-ft hospital that will replace the existing facility. The new hospital will feature 314 beds, with 80 per cent of beds in single-patient rooms. In August 2021 the hospital hit a major milestone with the final beam signing and topping off taking place. As well, two of the three tower cranes on site were dismantled in the summer of 2021, with the final crane to be dismantled in November 2021. Since the start of construction, significant progress has been made on the West Park Healthcare Centre redevelopment project, with more major milestones to be reached in 2022. By early 2022 the facility will be completely enclosed and will have permanent power on, followed by the start of commissioning.