Women’s College Hospital Redevelopment

Rank 2024

NR

Industry Sector: Health Care

Project Type: Health Care

Project Value: $460 million

Funding Source: P3

Province: Ontario

City / Region: Toronto

This hospital traces its history to 1883, and the Grenville Street complex was built in phases between the 1930s and the 1970s. The 400,000-square-foot replacement facility is being built in two phases on the current Grenville Street site. The redevelopment is targeting LEED-Silver certification and will replace all existing buildings, consolidating most hospital services into one location. Women’s College Hospital will have no patient beds; all of its programs are delivered on an outpatient basis.

Phase 1 was completed and occupied in May 2013, and demolition of the old structure is complete. The project is scheduled for completion in March 2016.

Project Owner: Women’s College Hospital

P3 Team Members/Project Team: Women’s College Partnership— Bilfinger Berger Project Investments, Black & McDonald/HSG Zander, Perkins Eastman Black/IBI Architects, The Walsh Group/ Bondfield Construction

Other Key Players: Infrastructure Ontario (procurement manager and project development); MMM Group (mechanical and electrical compliance); Engineering Harmonics Inc. (AV specialty consultants); Siemens (service contract for installed base)

Financiers and Banks: Banco Espirito Santo de Investimento, Credit Agricole Corporate, ING Capital, Société Générale.

Architect Names: Perkins Eastman Black/IBI Architects

Legal: McCarthy Tétrault LLP (advising Infrastructure Ontario and Women’s College Hospital)

2015 Rank: 91

2014 Rank: 91