Micoua-Saguenay Transmission Project

Rank 2024

NR

Image Credit: Hydro-Quebec

Industry Sector: Energy

Project Type: Transmission

Project Value: $1 billion

Funding Source: Public

Provincial Funding: $1 million

Province: Quebec

City / Region: Côte-Nord to Saguenay–Lac-Saint-Jean

Estimated End Date of Substantial Completion: 2023

The new 735-kilovolt transmission line will connect Hydro-Québec’s Micoua and Saguenay substations. The line will run roughly 262 kilometres through the Côte-Nord region (approx. 200 kilometres north of Quebec City) northwest through to the Saguenay–Lac-Saint-Jean region. The new line will help strengthen the reliability of the transmission system in the province. The project is scheduled for completion by the end of 2023. The last contracts were awarded in 2021, all the deforestation of the 262-kilometre line was completed in 2021.

Project Owner: Hydro-Québec

Contractor: Groupe Conseil Nutshimit Nippour (Section 8 clearing operations); Midifor Inc. (Section 9 and 10 clearing operations)

Other Key Players: Englobe

Supplier Other: Locweld (steel transmission towers)

Transmission Line Length (km): 262

2023 Rank: 61

2022 Rank: 59

2021 Rank: 68